THANKSGIVING 2019 UPDATE

WE ARE VERY THANKFUL FOR GREAT WEATHER AND A GREAT CONTRACTOR

WE CONTINUE TO BE ON TIME AND ON BUDGET

WORK OUTSIDE IS ALMOST COMPLETE – PARKING LOT IS BEING PAVED TODAY

IRRIGATION IS COMPLETE AND PLANTING WILL BEGIN MONDAY

OUTSIDE TRIM IS ALMOST COMPLETE WAITING ON THE SCREENS

THE RAILING WILL BE INSTALLED IN A COUPLE OF WEEKS

THE NORTH ROOM FLOORING IS COMPLETE SO TRIM OUT AND PAINTING WILL BEGIN

THE BATHROOMS ARE TAKING SHAPE

THE SOUTH EVENT ROOM IS ABOUT READY FOR PAINTING

THE HALL IS READY FOR FINAL PAINTING

THE PORCH CEILING IS PROGRESSING

THE LOUNGE CEILING IS FINISHED – WAITING ON THE LIGHT FIXTURE

THE FLAGPOLE IS UP – LIGHTS ARE BEING INSTALLED – OLD GLORY WILL FLY AGAIN SHORTLY

WORK ON THE SIGN HAS STARTED AND WILL FILL THIS EMPTY SPOT

NOVEMBER 18 UPDATE

THE NICE WEATHER YOU HAD WHILE I WAS CRUISING THE CARRIBEAN DELAYED SOME OUTSIDE ACTIVITY BUT WE ARE STILL ON SCHEDULE. ALL CURBS AND SIDEWALKS HAVE BEEN POURED AND THE PLASTIC REMOVED. THE PARKING LOT WILL BE REPAVED NEXT TUESDAY.

WORK INSIDE CONTINUES AT A SLOW BUT PERFECT PACE. THE NORTH END ROOM REMAINS THE SUPPLY AREA BUT THE TRIM WORK AND CEILING PROGRESSES

THE SECOND FLOOR STAIRS ARE COMPLETE SO PAINTING WILL BE COMPLETED

OF COURSE, THESE LEAD TO NO WHERE – ONLY STORAGE FOR NOW

THE ELEVATOR IS BEING COMPLETED AND INSPECTED AND SHOULD BE IN USE AS WE RECEIVE ITEMS FOR FIRST FLOOR

THE WOMENS RESTROOM IS TAKING SHAPE – FINAL PAINTING AND COUNTERTOPS ARE CLOSE

THE MENS RESTROOM IS ALSO PROGRESSING

THE MAIN SOUTH ROOM IS ALMOST COMPLETE – TRIM AND FINAL PAINTING

CEILING IS COMPLETE INCLUDING THE LIGHTING

THE FRONT HALL IS TAKING SHAPE

THE HALLWAY OUT TO THE PATIO LOOKS FANTASTIC – ALMOST COMPLETE

EXTERIOR PAINTING PROGRESSES NOW THAT THE WEATHER HAS CLEARED

THE FLAGPOLE IS NOW IN PLACE

ALL WALKS ARE IN – SCREENS HAVE NOT ARRIVED SO THE PATIO POST ARE NOT TRIMMED OUT

THE NORTH SIDE IS ALMOST COMPLETE

IRRIGATION IS GOING IN AND PLANTING WILL BE NEXT WEEK

NOVEMBER 7 UPDATE

A LOT OF OUTSIDE WORK HAS BEEN COMPLETED THIS WEEK

THE PARKING LOT WAS MILLED AND CLEANING UP THAT MESS CONTINUED TODAY

THE CURBS AND WALKWAYS GET POURED MONDAY

PAVING WILL BE COMPLETED MONDAY THE 18TH

EXTERIOR PAINTING HAS STARTED ON THE SOUTHWESTERN CORNER

THE AREA THAT GOT DESTROYED DURING DEMO HAS BEEN REJUVENATED SO OMNI GUEST HAVE A GOOD VIEW

THE PORCH AWAITS THE SCREEN ENCLOSURES BEFORE FINAL TRIMMING OUT CAN BE ACCOMPLISHED – PROBABLY ANOTHER TWO WEEKS

THE FRONT TRIM IS PAINTED AND READY FOR SIDING COAT

THE CEDAR WILL BE A TRANSLUCENT WHITE STAIN SO THE WOOD FEATURES WILL SHOW THRU AND MATCH THE TRIM COLOR

THE BAR AREA CEILING IS COMING ALONG – THAT IS TONGUE AND GROOVE AND VERY DIFFICULT TO MATCH UP – BUT IT LOOKS TERRIFIC

THE INTERIOR IS TAKING SHAPE – SOME ROOMS ARE TRIMMED OUT – DOORS ARE HUNG

AND TRASH CANS ARE FILLING AS CLEANUP BEGINS

THE MAIN EVENT ROOM IS GETTING TRIMMED OUT

THE KITCHEN IS BEING PLUMBED

THE MENS ROOM IS ALMOST COMPLETE EXCEPT FOR FIXTURES

THE WOMENS ROOM IS NEARING COMPLETION

THE MULTI PURPOSE ROOM HAS DOORS HUNG BUT WILL SERVE AS STAGING UNTIL THE VERY END

MORE CLEANING CONTINUES SO TRIM WORK CAN BEGIN

FINAL TRIM WORK ON THE PATIO – RAILING IS FOUR WEEKS OUT

NOVEMBER 1 UPDATE

IT HAS BEEN A GOOD MONTH FOR PROGRESS ON THE COMMUNITY CENTER

SIDING IS COMPLETE – CAULKING HAS STARTED – AND SOME TRIM BOARDS HAVE BEEN PAINTED. THE FINAL COLOR COAT WILL NOT GO ON UNTIL THE DUST SETTLES ON THE OUTSIDE WORK.

THE PARKING LOT WILL BE MILLED MONDAY/TUESDAY NEXT WEEK

CURBS WILL BE INSTALLED THE NEXT MONDAY/TUESDAY

BLACKTOP WILL GO DOWN MONDAY/TUESDAY THE NEXT

IRRIGATION FOR PHASE I OF LANDSCAPING IS COMPLETE. PLANTING ON THE SOUTH AND WEST SIDE STARTS MONDAY

PAVERS AND CONCRETE WALKS WILL BE FINISHED WHEN THE CURBS GO IN

THE PATIO WILL BE FINISHED AFTER THE SCREEN ROLLERS ARRIVE – NEXT TWO WEEKS

INSIDE WORK PROGRESSES AS WELL

DOORS ARE HUNG AND WIRING CONTINUES TO GET PULLED.

THE SHUTTERS SHOULD BE IN WITHIN TWO WEEKS

THE BAR IS BEING FABRICATED AT THE SHOP AND WILL BE IN PLACE IN A COUPLE WEEKS

ALL POWER IS TURNED ON AND LIGHT FIXTURES ARE BEING INSTALLED

THE CEILING TILES ARE BEING INSTALLED AT THE SAME TIME

BATHROOMS ARE TAKING SHAPE

MIRRORS ARE HUNG TO MAKE SURE FIXTURES ARE CENTERED

THE FINAL ROOM TO BE FINISHED IS THE “CARD ROOM”

ALL SERVICES ARE LOCATED OFF THIS SO THIS SERVES AS A STORAGE AREA.

OCTOBER 19 UPDATE

A LOT HAS HAPPENED THIS WEEK.

THE FRONT ENTRANCE IS COMPLETE. THE RAMP AND STEPS WILL BE FINISHED NEXT WEEK.

ALL MATERIAL IS BEING REMOVED FROM THE PARKING LOT SO MILLING AND REPAVING CAN BE COMPLETED IN THE NEXT COUPLE OF WEEKS. THIS IS WEATHER AND CONTRACTOR DEPENDENT, BUT WE WILL BE READY

IRRIGATION WORK HAS STARTED IN PREPARATION FOR LANDSCAPING

FINAL OUTSIDE TRIM IS BEING COMPLETED AND PAINTING WILL CONTINUE ON THE FIRST LEVEL

INSIDE FLOOR TILE IS PROGRESSING. THIS IS A VERY SLOW PROCESS BUT WILL BE BEAUTIFUL. THIS IS THE SOUTH VIEW LOOKING OUT ON THE DECK

THAT’S THE FIREPLACE ON THE LEFT – THREE SIDED. LARRY YOU WILL LOVE IT

THE LOUNGE IS ALSO PROGRESSING. THE BIFOLD PANELS AND BAR AREA WILL BE COMPLETED THE SECOND WEEK OF NOVEMBER.

ANOTHER SECTION COMPLETED

THE MAIN EVENT ROOM IS TAKING SHAPE. FLOORING IS COMPLETE. CEILING TILES ARE GOING IN. SPRINKLER IS COMPLETE. A/C AND LIGHTING IS GOING IN

DOORS ARE BEING HUNG. ALL HAVE BEEN DELIVERED.

THE MULTI PURPOSE ROOM HAS BECOME THE SUPPLY ROOM. CEILING IS COMPLETE BUT FLOORING WILL BE THE LAST ONE COMPLETED.

THE TILE IN THE WOMENS RESTROOM IS COMPLETE

THIS WILL BE THE SINK AREA

THIS WILL BE THE HCP AREA

THE MEN CAME IN SECOND BUT IS BEING COMPLETED

THE PORCH CEILING HAS BEEN STARTED.

THIS SAME CEILING WILL BE IN THE LOUNGE AREA

THE PAVERS START MONDAY SO THE DECK AND PORCH WILL BE COMPLETED BY WEEKS END

OCTOBER 5 UPDATE

A LOT HAS BEEN ACCOMPLISHED THIS WEEK

THE FINAL SHINGLES WERE PLACED TODAY

THE SCREEN PORCH IS TOTALLY FRAMED AWAITING TRIM

THE DRAIN BED IS COMPLETE AND GRADED

THE DUMPSTER AREA IS TAKING SHAPE – THIS WILL BE HIDDEN WITH LANDSCAPE

THIS IS THE FINAL COLOR – TAN WITH WHITE TRIM

THE INTERIOR IS GETTING CLEANED UP AND PREPPED FOR TILE

LOOKING OUT TOWARDS THE PATIO

THE FLOOR TILE IN THE MAIN ROOM HAS STARTED

THE PEGS ARE A NEW SYSTEM FOR LAYING, SPACING, AND LEVELING ALL AT ONCE

THE GROUTING WILL BE DONE WHEN ALL IS COMPLETE

THIS TILE WILL BE THROUGHOUT THE FIRST FLOOR WHICH WILL GIVE A UNIFORM LOOK AND FLOW BETWEEN ROOMS

A CLOSEUP OF THE SYSTEM

THESE GUYS ARE REAL ARTIST

THE FRONT DOOR WILL BE A SINGLE WIDE DOOR FRAMED IN GLASS

THE MENS ROOM FLOOR IS COMPLETE

THE WALL TILE IS NEXT

THE WOMENS ROOM FLOOR IS ALSO FINISHED

THE WALL TILE HAS STARTED

THE SAME PEG SYSTEM IS USED TO INSTALL THE WALL TILE

THE STAIRS TO THE SECOND FLOOR ARE COMPLETE

THE ELEVATOR IS ABOUT HALF COMPLETE

THE SECOND FLOOR IS “COMPLETE”

THE CONSTRUCTION OFFICE IS LOCATED HERE UNTIL PROJECT IS COMPLETED

THIS IS THE “F U T U R E”

THIS IS THE NORTH END OF SECOND FLOOR

THIS WILL BE STORAGE – TABLES/CHAIRS ETC

RESTROOMS ARE PLUMBED AND WILL SEPARATE STORAGE AND FUTURE SPACE

THEY ARE NOT GOING IN NOW

THE CEILING GRID HAS STARTED

THE CEILING WILL BE TRIMMED OUT IN WHITE WASHED CEDAR

SCREEN PORCH IS COMPLETE AND AWAITS TRIM

THE PATIO IS READY FOR PAVERS

FRONT PORCH/ENTRY IS COMPLETE AND STEPS POURED

THIS IS THE FINAL COLOR SCHEME

THE PAVERS ARE IN THE PARKING LOT AND WILL BE PLACED IN A WEEK OR SO AS SOON AS ALL EXTERIOR TRIM IS COMPLETE

A/C UNITS HAVE BEEN INSTALLED ALONG WITH FIRE, WATER, IRRIGATION

SEPTEMBER 28 UPDATE

GREAT PROGRESS HAS BEEN MADE THIS WEEK

THE SCREEN PORCH IS ALMOST FRAMED

THE PATIO DECK WALL IS ALMOST COMPLETE

THE PAVERS WILL BE PLACED NEXT WEEK

WHAT A FANTASTIC VIEW FROM THE DECK AND SCREEN PORCH

THE REAR SIDING IS ALMOST COMPLETE

THEN THE PAVER WALKWAY WILL BE EXTENDED TO THE BOTTOM OF THE STAIRS

THE STAIRS WILL THEN BE FINISHED AND HANDRAILS PUT ON

THIS IS THE VIEW FROM THE GOLF COURSE

THE CONSTRUCTION FENCE WILL COME DOWN AND LANDSCAPING INSTALLED

THE WALL FOLLOWS THE PROPERTY LINE

ONCE THE WALKWAY IS IN PLACE, THE FENCE WILL COME DOWN AND LANDSCAPING INSTALLED

SCREEN PORCH ALMOST FRAMED

PLACING THE FINAL PIECES ON THE FRONT WALL

FRONT ENTRANCE IS COMPLETE EXCEPT FOR THE DOOR

GROUND HAS BEEN CLEARED FOR THE ENTRANCE WALKS

ALL A/C UNITS IN PLACE AND SECOND FLOOR UNITS RUNNING TO REDUCE HUMIDITY ON FIRST FLOOR SO DRYWALL AND PAINTING CAN CONTINUE

DECK BASE IS READY FOR PAVERS

FRONT WALL IS ALMOST COMPLETE

SOME OF FIRST FLOOR IS FINISHED EXCEPT FOR FINAL PAINT

THIS CEILING WILL BE TRIMMED IN WOOD

THE KITCHEN FLOOR IS ALMOST COMPLETE

THE MEN’S ROOM FLOOR IS ALMOST FINISHED

SECOND FLOOR IS COMPLETE AND THE CONSTRUCTION OFFICE HAS MOVED IN SO PARKING LOT CAN BE CLEARED

THE AIR HANDLERS ARE CLEAR OF THE FLOOR SPACE