JULY 3 UPDATE

HAPPY HOLIDAY !!🇺🇸 🇺🇸 🇺🇸

THE JOB IS SHUT DOWN UNTIL MONDAY FOR THE HOLIDAY

THE POWER IS READY FOR THE TRANSFER JULY 9 – ACCORDING TO FPU

THE ROOFERS HAVE MUCH TO DO BUT THIS WEATHER IS TOUGH – BUT THEY ARE NOT HOLDING ANYTHING UP.

MUCH MATERIAL HAS BEEN DELIVERED FOR INTERIOR INSULATION AND HVAC

ALL WINDOWS THAT HAVE BEEN DELIVERED ARE INSTALLED

ALL OTHERS HAVE BEEN MEASURED AND ARE FOUR WEEKS OUT

ALL BLUE INSULATION HAS BEEN COMPLETED

THE FRONT PORCH BEAMS MIGHT BE DELIVERED MID WEEK NEXT WEEK AND THEN THE FRAMERS WILL COMPLETE THE FRONT

JUNE 28 UPDATE

A LOT HAS GONE ON THIS WEEK. THE WATER MAIN IS CONNECTED. THE POWER EQUIPMENT IS BEING INSTALLED AND WILL BE SWITCHED OVER JULY 9. A LOT OF PLUMBING INSIDE HAS BEEN ROUGHED IN. WIRING WILL START MONDAY AS WILL HVAC DUCTWORK. OVER HALF OF THE WINDOWS ARE INSTALLED. ALL ROOFING HAS BEEN DRIED IN. DICKY SMITH CONTINUES DOING A FANTASTIC JOB FOR US.

THE PICTURES FOLLOWING WILL GIVE YOU AN OVERVIEW AS OF 4 TODAY. NO WORK TOMORROW AND NEXT WEEK WILL BE A SHORT ONE DUE TO THE HOLIDAY.

WORK WILL PICK UP FULL STEAM MONDAY JULY 8 WORKING SATURDAYS AS WELL.

WE ARE STILL ON TIME AND ON BUDGET.

HAVE A GREAT HOLIDAY !!! OLD GLORY STILL FLYS PROUDLY.

JUNE 15 UPDATE

THE LAST ROOF STRUCTURE IS BEING COMPLETED OVER THE BAR/SCREEN PORCH

SECOND FLOOR IS GETTING CLEANED UP

STEPS ARE POURED

FIRST FLOOR FRAMING HAS STARTED – EVENT ROOMS

MAIN HALL WAY – EVENT ROOMS RIGHT – LODGE LEFT

BAR / SCREENED PORCH ROOF IS ALMOST COMPLETE

REST ROOMS ARE PLUMED

EVENT ROOMS

CARD ROOM

FINAL PART OF BLOCK INSULATION ROLLED ON BEFORE FRAMING STARTS

JUNE 8 UPDATE

THE FINAL ROOF PIECE IS STARTED – WAITING ON THE TRUSSES TO BE BUILT

ALL OTHER TRUSSES ARE IN PLACE

ROOF SHEETING HAS STARTED – FRIDAY

LOWER ROOF IS COMPLETE

STARTING ON THE UPPER

THE FRONT ENTRANCE IS TAKING SHAPE

THE ROOF SUPPORT POST SHOULD BE IN IN A COUPLE WEEKS – FOOTERS ARE POURED

FIRST FLOOR IS CLEANED UP READY FOR FRAMING TO BEGIN – POSSIBLY NEXT WEEK

FIRST FLOOR LOOKING TOWARDS THE BAR

SECOND FLOOR ROOF IS ALMOST COMPLETE

THIS IS ALL THAT IS LEFT TO SHEET AND BY THE TIME YOU GET THIS, IT WILL BE COMPLETED

OLD GLORY CONTINUES TO FLY AND WILL BE MOVED AFTER THIS SECTION IS DONE

IT WILL CONTINUE TO FLY UNTIL THE POLE GETS ERECTED

OUR GREAT WORKING SUPERINTENDENT IS KNOCKING DOWN THE SCAFFOLDING

WHILE THEY FINISH SHEETING – AND THIS IS SATURDAY

THE BLUE WATERPROOF SEAL IS ALMOST COMPLETE ALSO

MAY 31 UPDATE

FIRST FLOOR IS CLEANED UP AND ALL EXTRA SUPPORT POST ARE REMOVED

MOST ROOF TRUSSES HAVE BEEN PUT IN PLACE

ALL ROOF TRUSSES ARE IN PLACE

THE SOFFIT IS BEGINNING TO TAKE SHAPE

THE ELEVATOR SHAFT IS COMPLETE – THE BLUE IS A WEATHER SEAL

THE UPPER ROOF STRUCTURE IS COMPLETE

THE SHEETING GOES DOWN TUESDAY