Friday AM Update

All is good. The permit package is delivered. There is no delay at this point. We will follow progress closely. GB is still the 19th.

The slab between buildings will be broken up at 2 this afternoon with Omni contractors/plumbers present. Marsh View is not scheduled to reopen until Monday so there are no issues there. After water repair, the tarp will be removed and the last piece of the roof will be removed – we are doing that as a favor (no real cost). Then we are totally separated and the rest is up to Omni to rebuild the wall.

Actual construction is scheduled to start after the first of the year. Between now and then all fill and grading will take place. They won’t be sitting still. The well head will be grouted in that time period also.

IMG_3400

IMG_3403

The slab area is being cleared.

IMG_3405

This pile will be hauled this afternoon and Saturday AM. Then the remaining corner will come down along with the trees in that corner.

IMG_3406
IMG_3407

Total separation.

IMG_3408

Last section to come down.

All for now.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s