APRIL 4 UPDATE

THE FIRST FLOOR WALLS ARE COMPLETE AND ABOUT HALF OF THE STEEL HAS BEEN ERECTED. ALL WALLS HAVE BEEN FILLED AND THE LARGE CONCRETE BEAMS AT THE SOUTH END ARE FORMED AND POURED.

NEXT WEEK THE REST OF THE STEEL WILL BE ERECTED AND THE FORMS KNOCKED OFF THE CONCRETE BEAMS. THESE BEAMS WILL ALLOW US TO HAVE THE VERY LARGE WINDOWS WE WANTED.

ASSUMING NO WEATHER DELAYS, THE HOLLOW CORE PIECES WILL BE DELIVERED MONDAY THE 15TH. THEN WORK WILL BEGIN ON THE SECOND FLOOR.