HOLLOW CORE UPDATE 2

THE CRANE WAS SET UP AND READY AT 7:30. THE FIRST TRUCKS ARRIVED AT 8:15

WORK CONTINUED ALL DAY WITH VERY FEW TRAFFIC DELAYS.

ALL WAS COMPLETED BY 4:30, INCLUDING GROUTING. ALL THE SEAMS BETWEEN THE SLABS ARE FILLED WITH A GROUT THAT FORMS A BOND

FOLLOW THE PICS AND CHECK THE PROGRESS. THE CONTRACTOR DID A GREAT JOB

THE NEXT STEP IS FRAMING THE SECOND FLOOR TO GET READY TO POUR THE SLAB. THIS WILL BE A TWO INCH POUR ON TOP OF THE HOLLOW CORE BASE. THIS WILL NOT HAPPEN FOR ABOUT 10 DAYS AS THE GROUT MUST CURE.

D4F996CB-271E-43BE-8274-E0AF37D5BB42

THE LARGE SLABS WERE FIRST

6B9E2011-2812-4FF0-8326-C8A429580F96

GROUTING THE SEAMS

F9E952E0-409D-4E5B-8D11-4C93D73EB761614C6B46-C8D8-4E16-AFEC-00104C55AD54549BEDB5-47AF-4ADF-B223-E33F668512B6

THE SHORT SLABS AWAIT COMPLETION OF THE LARGE ONES

8D7B33F8-2E7B-4D05-B9D2-BEEBB8DF28C1

THE TOP OUT STEEL BEAM OVER THE BAR AREA

5CE9FBB2-1984-4A35-8A69-8EAED7165C2D549B3C06-91B6-4BB8-9F0A-F8E8D9ACA200

THE MAIN ROOM

ADF73601-3444-4F92-BD4D-641E2C18E0C9

THE “CARD” ROOM AREA

760DE59D-F6F1-4943-8687-D6E80B21B766

THE LAST SMALL PIECE GOES IN PLACE

AC03098F-93A2-4D44-851F-462FC92A48AD

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s