MAY 7 UPDATE

THE PROJECT IS MOVING ALONG FINE.

THE SECOND FLOOR SLAB HAS BEEN POURED AND CURING

THE MASONS ARE LAYING THE BLOCK FOR THE BACK AND BOTH SIDE WALLS. THEY LAY ABOUT 1000 BLOCKS A DAY

THE SUPPORT COLUMNS WILL BE POURED EARLY THIS WEEK

THE FRAMERS WILL THEN FRAME THE FRONT WALL AND ROOF WORK WILL BEGIN

THE ROOF TRUSSES WILL BE DELIVERED WEEKS END OR EARLY NEXT WEEK

SHINGLES HAVE BEEN ORDERED AND ARE 6-8 WEEKS OUT.

ONCE UNDER ROOF WORK WILL BEGIN INSIDE

WEATHER HAS BEEN GREAT SO KEEP YOUR FINGERS AND TOES CROSSED IT CONTINUES.

IMG_0254

IMG_0252

IMG_0248

IMG_0246

IMG_0244

IMG_0243

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s