JULY 3 UPDATE

HAPPY HOLIDAY !!🇺🇸 🇺🇸 🇺🇸

THE JOB IS SHUT DOWN UNTIL MONDAY FOR THE HOLIDAY

THE POWER IS READY FOR THE TRANSFER JULY 9 – ACCORDING TO FPU

THE ROOFERS HAVE MUCH TO DO BUT THIS WEATHER IS TOUGH – BUT THEY ARE NOT HOLDING ANYTHING UP.

MUCH MATERIAL HAS BEEN DELIVERED FOR INTERIOR INSULATION AND HVAC

ALL WINDOWS THAT HAVE BEEN DELIVERED ARE INSTALLED

ALL OTHERS HAVE BEEN MEASURED AND ARE FOUR WEEKS OUT

ALL BLUE INSULATION HAS BEEN COMPLETED

THE FRONT PORCH BEAMS MIGHT BE DELIVERED MID WEEK NEXT WEEK AND THEN THE FRAMERS WILL COMPLETE THE FRONT