JULY 18 UPDATE

THE PROJECT CONTINUES TO PROGRESS ON SCHEDULE – AND ON BUDGET.

THE WEATHER, FPU, AND THE COUNTY INSPECTORS CONTINUE TO COOPERATE. THE NEW TRANSFORMER IS OPERATIONAL AND WE HAVE TEMPORARY POWER. NO MORE GENERATORS AND THE ELEVATOR CAN BE INSTALLED.

THERE IS A LOT GOING ON AND MANY CONTRACTORS INVOLVED AT THE SAME TIME. MOST OF THE WORK IS INTERIOR SO NOT MUCH VISIBLE FROM THE OUTSIDE

THESE PICS WILL GIVE YOU AN IDEA OF THE COMPLEXITY OF WHAT IS GOING ON

THE KITCHEN WITH DOUBLE DOORS FOR CATERER ACCESS

THE AIR HANDLERS HAVE BEEN DELIVERED TO THE SECOND FLOOR USING THE OPEN WINDOW, WHICH WILL NOW BE INSTALLED

THE FINAL STRAPPING OF THE ROOF TRUSSES IS BEING COMPLETED

THE HALLWAY DUCTWORK IS WELL UNDERWAY AS WELL AS SPRINKLER SYSTEM

A LOT OF THE CEILING WORK HAS BEEN COMPLETED AND WALL INSULATION

THE SCREENED PORCH FOUNDATION HAS BEEN POURED

THE SIDING ON THE SOUTH WALL HAS BEEN STARTED

THE UPPER ROOF WILL BE COMPLETED TOMORROW

SOFFIT TRIM AND PAINTING WILL BEGIN AND THE LOWER ROOF WILL BE COMPLETED IN A COUPLE WEEKS AFTER THAT IS COMPLETED

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s