NOVEMBER 1 UPDATE

IT HAS BEEN A GOOD MONTH FOR PROGRESS ON THE COMMUNITY CENTER

SIDING IS COMPLETE – CAULKING HAS STARTED – AND SOME TRIM BOARDS HAVE BEEN PAINTED. THE FINAL COLOR COAT WILL NOT GO ON UNTIL THE DUST SETTLES ON THE OUTSIDE WORK.

THE PARKING LOT WILL BE MILLED MONDAY/TUESDAY NEXT WEEK

CURBS WILL BE INSTALLED THE NEXT MONDAY/TUESDAY

BLACKTOP WILL GO DOWN MONDAY/TUESDAY THE NEXT

IRRIGATION FOR PHASE I OF LANDSCAPING IS COMPLETE. PLANTING ON THE SOUTH AND WEST SIDE STARTS MONDAY

PAVERS AND CONCRETE WALKS WILL BE FINISHED WHEN THE CURBS GO IN

THE PATIO WILL BE FINISHED AFTER THE SCREEN ROLLERS ARRIVE – NEXT TWO WEEKS

INSIDE WORK PROGRESSES AS WELL

DOORS ARE HUNG AND WIRING CONTINUES TO GET PULLED.

THE SHUTTERS SHOULD BE IN WITHIN TWO WEEKS

THE BAR IS BEING FABRICATED AT THE SHOP AND WILL BE IN PLACE IN A COUPLE WEEKS

ALL POWER IS TURNED ON AND LIGHT FIXTURES ARE BEING INSTALLED

THE CEILING TILES ARE BEING INSTALLED AT THE SAME TIME

BATHROOMS ARE TAKING SHAPE

MIRRORS ARE HUNG TO MAKE SURE FIXTURES ARE CENTERED

THE FINAL ROOM TO BE FINISHED IS THE “CARD ROOM”

ALL SERVICES ARE LOCATED OFF THIS SO THIS SERVES AS A STORAGE AREA.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s