NOVEMBER 7 UPDATE

A LOT OF OUTSIDE WORK HAS BEEN COMPLETED THIS WEEK

THE PARKING LOT WAS MILLED AND CLEANING UP THAT MESS CONTINUED TODAY

THE CURBS AND WALKWAYS GET POURED MONDAY

PAVING WILL BE COMPLETED MONDAY THE 18TH

EXTERIOR PAINTING HAS STARTED ON THE SOUTHWESTERN CORNER

THE AREA THAT GOT DESTROYED DURING DEMO HAS BEEN REJUVENATED SO OMNI GUEST HAVE A GOOD VIEW

THE PORCH AWAITS THE SCREEN ENCLOSURES BEFORE FINAL TRIMMING OUT CAN BE ACCOMPLISHED – PROBABLY ANOTHER TWO WEEKS

THE FRONT TRIM IS PAINTED AND READY FOR SIDING COAT

THE CEDAR WILL BE A TRANSLUCENT WHITE STAIN SO THE WOOD FEATURES WILL SHOW THRU AND MATCH THE TRIM COLOR

THE BAR AREA CEILING IS COMING ALONG – THAT IS TONGUE AND GROOVE AND VERY DIFFICULT TO MATCH UP – BUT IT LOOKS TERRIFIC

THE INTERIOR IS TAKING SHAPE – SOME ROOMS ARE TRIMMED OUT – DOORS ARE HUNG

AND TRASH CANS ARE FILLING AS CLEANUP BEGINS

THE MAIN EVENT ROOM IS GETTING TRIMMED OUT

THE KITCHEN IS BEING PLUMBED

THE MENS ROOM IS ALMOST COMPLETE EXCEPT FOR FIXTURES

THE WOMENS ROOM IS NEARING COMPLETION

THE MULTI PURPOSE ROOM HAS DOORS HUNG BUT WILL SERVE AS STAGING UNTIL THE VERY END

MORE CLEANING CONTINUES SO TRIM WORK CAN BEGIN

FINAL TRIM WORK ON THE PATIO – RAILING IS FOUR WEEKS OUT

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s