DECEMBER 11 UPDATE

WOW, THANKSGIVING IS OVER AND IT’S ALMOST CHRISTMAS

THE OAKS PROGRESSES AT THE SAME PACE

PARKING LOT IS PAVED – STRIPPING HAPPENS AS SOON AS THE WEATHER COOPERATES

MOST OF THE LANDSCAPING IS IN – JUST IN TIME FOR RAIN – BUT THE IRRIGATION SYSTEM IS COMPLETE

MOST OF THE EXTERIOR TRIM AND PAINTING IS COMPLETE

EXTERIOR LIGHTS ARE MAINLY INSTALLED

THE PICTURES SPEAK FOR THEMSELVES

THE LAST ONE IS THE SECOND FLOOR CLEARED OUT – READY FOR STORAGE AND ????

THERE IS A LOT OF INTERIOR FINISH TO BE COMPLETED

BUT, THE PROJECT IS STILL ON TIME AND ON BUDGET.