AUGUST 7 UPDATE

WORK IS PROGRESSING ON SCHEDULE ON MANY FRONTS

FOAM INSULATION HAS BEEN COMPLETED IN ALL ROOF AREAS

DUCT WORK IS IN FINAL STAGES

THE FIREPLACE HAS BEEN INSTALLED

MORE FOAM INSULATION

DRYWALL HAS STARTED

NORTH WALL TRIM HAS STARTED

JULY 29 UPDATE

THE BAR IS COMPLETELY FRAMED WAITING ON DOORS

THE MAIN DECK DOORS ARE GOING IN AS WE SPEAK

LOTS OF WALL INSULATION IS COMPLETED AND A LOT OF SOFFIT WORK DONE

WIRING HAS STARTED

SIDING ON THE SOUTH SIDE HAS BEEN STARTED

THE SCREEN PORCH IS FRAMED

DOOR INSTALLATION IN PROGRESS

UPPER WINDOWS ARE COMPLETE

ONCE THAT IS COMPLETE AND FRAMED THE LOWER ROOF WILL BE FINISHED

JULY 18 UPDATE

THE PROJECT CONTINUES TO PROGRESS ON SCHEDULE – AND ON BUDGET.

THE WEATHER, FPU, AND THE COUNTY INSPECTORS CONTINUE TO COOPERATE. THE NEW TRANSFORMER IS OPERATIONAL AND WE HAVE TEMPORARY POWER. NO MORE GENERATORS AND THE ELEVATOR CAN BE INSTALLED.

THERE IS A LOT GOING ON AND MANY CONTRACTORS INVOLVED AT THE SAME TIME. MOST OF THE WORK IS INTERIOR SO NOT MUCH VISIBLE FROM THE OUTSIDE

THESE PICS WILL GIVE YOU AN IDEA OF THE COMPLEXITY OF WHAT IS GOING ON

THE KITCHEN WITH DOUBLE DOORS FOR CATERER ACCESS

THE AIR HANDLERS HAVE BEEN DELIVERED TO THE SECOND FLOOR USING THE OPEN WINDOW, WHICH WILL NOW BE INSTALLED

THE FINAL STRAPPING OF THE ROOF TRUSSES IS BEING COMPLETED

THE HALLWAY DUCTWORK IS WELL UNDERWAY AS WELL AS SPRINKLER SYSTEM

A LOT OF THE CEILING WORK HAS BEEN COMPLETED AND WALL INSULATION

THE SCREENED PORCH FOUNDATION HAS BEEN POURED

THE SIDING ON THE SOUTH WALL HAS BEEN STARTED

THE UPPER ROOF WILL BE COMPLETED TOMORROW

SOFFIT TRIM AND PAINTING WILL BEGIN AND THE LOWER ROOF WILL BE COMPLETED IN A COUPLE WEEKS AFTER THAT IS COMPLETED

JULY 3 UPDATE

HAPPY HOLIDAY !!🇺🇸 🇺🇸 🇺🇸

THE JOB IS SHUT DOWN UNTIL MONDAY FOR THE HOLIDAY

THE POWER IS READY FOR THE TRANSFER JULY 9 – ACCORDING TO FPU

THE ROOFERS HAVE MUCH TO DO BUT THIS WEATHER IS TOUGH – BUT THEY ARE NOT HOLDING ANYTHING UP.

MUCH MATERIAL HAS BEEN DELIVERED FOR INTERIOR INSULATION AND HVAC

ALL WINDOWS THAT HAVE BEEN DELIVERED ARE INSTALLED

ALL OTHERS HAVE BEEN MEASURED AND ARE FOUR WEEKS OUT

ALL BLUE INSULATION HAS BEEN COMPLETED

THE FRONT PORCH BEAMS MIGHT BE DELIVERED MID WEEK NEXT WEEK AND THEN THE FRAMERS WILL COMPLETE THE FRONT

JUNE 28 UPDATE

A LOT HAS GONE ON THIS WEEK. THE WATER MAIN IS CONNECTED. THE POWER EQUIPMENT IS BEING INSTALLED AND WILL BE SWITCHED OVER JULY 9. A LOT OF PLUMBING INSIDE HAS BEEN ROUGHED IN. WIRING WILL START MONDAY AS WILL HVAC DUCTWORK. OVER HALF OF THE WINDOWS ARE INSTALLED. ALL ROOFING HAS BEEN DRIED IN. DICKY SMITH CONTINUES DOING A FANTASTIC JOB FOR US.

THE PICTURES FOLLOWING WILL GIVE YOU AN OVERVIEW AS OF 4 TODAY. NO WORK TOMORROW AND NEXT WEEK WILL BE A SHORT ONE DUE TO THE HOLIDAY.

WORK WILL PICK UP FULL STEAM MONDAY JULY 8 WORKING SATURDAYS AS WELL.

WE ARE STILL ON TIME AND ON BUDGET.

HAVE A GREAT HOLIDAY !!! OLD GLORY STILL FLYS PROUDLY.

JUNE 15 UPDATE

THE LAST ROOF STRUCTURE IS BEING COMPLETED OVER THE BAR/SCREEN PORCH

SECOND FLOOR IS GETTING CLEANED UP

STEPS ARE POURED

FIRST FLOOR FRAMING HAS STARTED – EVENT ROOMS

MAIN HALL WAY – EVENT ROOMS RIGHT – LODGE LEFT

BAR / SCREENED PORCH ROOF IS ALMOST COMPLETE

REST ROOMS ARE PLUMED

EVENT ROOMS

CARD ROOM

FINAL PART OF BLOCK INSULATION ROLLED ON BEFORE FRAMING STARTS