NOVEMBER 1 UPDATE

IT HAS BEEN A GOOD MONTH FOR PROGRESS ON THE COMMUNITY CENTER

SIDING IS COMPLETE – CAULKING HAS STARTED – AND SOME TRIM BOARDS HAVE BEEN PAINTED. THE FINAL COLOR COAT WILL NOT GO ON UNTIL THE DUST SETTLES ON THE OUTSIDE WORK.

THE PARKING LOT WILL BE MILLED MONDAY/TUESDAY NEXT WEEK

CURBS WILL BE INSTALLED THE NEXT MONDAY/TUESDAY

BLACKTOP WILL GO DOWN MONDAY/TUESDAY THE NEXT

IRRIGATION FOR PHASE I OF LANDSCAPING IS COMPLETE. PLANTING ON THE SOUTH AND WEST SIDE STARTS MONDAY

PAVERS AND CONCRETE WALKS WILL BE FINISHED WHEN THE CURBS GO IN

THE PATIO WILL BE FINISHED AFTER THE SCREEN ROLLERS ARRIVE – NEXT TWO WEEKS

INSIDE WORK PROGRESSES AS WELL

DOORS ARE HUNG AND WIRING CONTINUES TO GET PULLED.

THE SHUTTERS SHOULD BE IN WITHIN TWO WEEKS

THE BAR IS BEING FABRICATED AT THE SHOP AND WILL BE IN PLACE IN A COUPLE WEEKS

ALL POWER IS TURNED ON AND LIGHT FIXTURES ARE BEING INSTALLED

THE CEILING TILES ARE BEING INSTALLED AT THE SAME TIME

BATHROOMS ARE TAKING SHAPE

MIRRORS ARE HUNG TO MAKE SURE FIXTURES ARE CENTERED

THE FINAL ROOM TO BE FINISHED IS THE “CARD ROOM”

ALL SERVICES ARE LOCATED OFF THIS SO THIS SERVES AS A STORAGE AREA.

OCTOBER 19 UPDATE

A LOT HAS HAPPENED THIS WEEK.

THE FRONT ENTRANCE IS COMPLETE. THE RAMP AND STEPS WILL BE FINISHED NEXT WEEK.

ALL MATERIAL IS BEING REMOVED FROM THE PARKING LOT SO MILLING AND REPAVING CAN BE COMPLETED IN THE NEXT COUPLE OF WEEKS. THIS IS WEATHER AND CONTRACTOR DEPENDENT, BUT WE WILL BE READY

IRRIGATION WORK HAS STARTED IN PREPARATION FOR LANDSCAPING

FINAL OUTSIDE TRIM IS BEING COMPLETED AND PAINTING WILL CONTINUE ON THE FIRST LEVEL

INSIDE FLOOR TILE IS PROGRESSING. THIS IS A VERY SLOW PROCESS BUT WILL BE BEAUTIFUL. THIS IS THE SOUTH VIEW LOOKING OUT ON THE DECK

THAT’S THE FIREPLACE ON THE LEFT – THREE SIDED. LARRY YOU WILL LOVE IT

THE LOUNGE IS ALSO PROGRESSING. THE BIFOLD PANELS AND BAR AREA WILL BE COMPLETED THE SECOND WEEK OF NOVEMBER.

ANOTHER SECTION COMPLETED

THE MAIN EVENT ROOM IS TAKING SHAPE. FLOORING IS COMPLETE. CEILING TILES ARE GOING IN. SPRINKLER IS COMPLETE. A/C AND LIGHTING IS GOING IN

DOORS ARE BEING HUNG. ALL HAVE BEEN DELIVERED.

THE MULTI PURPOSE ROOM HAS BECOME THE SUPPLY ROOM. CEILING IS COMPLETE BUT FLOORING WILL BE THE LAST ONE COMPLETED.

THE TILE IN THE WOMENS RESTROOM IS COMPLETE

THIS WILL BE THE SINK AREA

THIS WILL BE THE HCP AREA

THE MEN CAME IN SECOND BUT IS BEING COMPLETED

THE PORCH CEILING HAS BEEN STARTED.

THIS SAME CEILING WILL BE IN THE LOUNGE AREA

THE PAVERS START MONDAY SO THE DECK AND PORCH WILL BE COMPLETED BY WEEKS END

OCTOBER 5 UPDATE

A LOT HAS BEEN ACCOMPLISHED THIS WEEK

THE FINAL SHINGLES WERE PLACED TODAY

THE SCREEN PORCH IS TOTALLY FRAMED AWAITING TRIM

THE DRAIN BED IS COMPLETE AND GRADED

THE DUMPSTER AREA IS TAKING SHAPE – THIS WILL BE HIDDEN WITH LANDSCAPE

THIS IS THE FINAL COLOR – TAN WITH WHITE TRIM

THE INTERIOR IS GETTING CLEANED UP AND PREPPED FOR TILE

LOOKING OUT TOWARDS THE PATIO

THE FLOOR TILE IN THE MAIN ROOM HAS STARTED

THE PEGS ARE A NEW SYSTEM FOR LAYING, SPACING, AND LEVELING ALL AT ONCE

THE GROUTING WILL BE DONE WHEN ALL IS COMPLETE

THIS TILE WILL BE THROUGHOUT THE FIRST FLOOR WHICH WILL GIVE A UNIFORM LOOK AND FLOW BETWEEN ROOMS

A CLOSEUP OF THE SYSTEM

THESE GUYS ARE REAL ARTIST

THE FRONT DOOR WILL BE A SINGLE WIDE DOOR FRAMED IN GLASS

THE MENS ROOM FLOOR IS COMPLETE

THE WALL TILE IS NEXT

THE WOMENS ROOM FLOOR IS ALSO FINISHED

THE WALL TILE HAS STARTED

THE SAME PEG SYSTEM IS USED TO INSTALL THE WALL TILE

THE STAIRS TO THE SECOND FLOOR ARE COMPLETE

THE ELEVATOR IS ABOUT HALF COMPLETE

THE SECOND FLOOR IS “COMPLETE”

THE CONSTRUCTION OFFICE IS LOCATED HERE UNTIL PROJECT IS COMPLETED

THIS IS THE “F U T U R E”

THIS IS THE NORTH END OF SECOND FLOOR

THIS WILL BE STORAGE – TABLES/CHAIRS ETC

RESTROOMS ARE PLUMBED AND WILL SEPARATE STORAGE AND FUTURE SPACE

THEY ARE NOT GOING IN NOW

THE CEILING GRID HAS STARTED

THE CEILING WILL BE TRIMMED OUT IN WHITE WASHED CEDAR

SCREEN PORCH IS COMPLETE AND AWAITS TRIM

THE PATIO IS READY FOR PAVERS

FRONT PORCH/ENTRY IS COMPLETE AND STEPS POURED

THIS IS THE FINAL COLOR SCHEME

THE PAVERS ARE IN THE PARKING LOT AND WILL BE PLACED IN A WEEK OR SO AS SOON AS ALL EXTERIOR TRIM IS COMPLETE

A/C UNITS HAVE BEEN INSTALLED ALONG WITH FIRE, WATER, IRRIGATION

SEPTEMBER 28 UPDATE

GREAT PROGRESS HAS BEEN MADE THIS WEEK

THE SCREEN PORCH IS ALMOST FRAMED

THE PATIO DECK WALL IS ALMOST COMPLETE

THE PAVERS WILL BE PLACED NEXT WEEK

WHAT A FANTASTIC VIEW FROM THE DECK AND SCREEN PORCH

THE REAR SIDING IS ALMOST COMPLETE

THEN THE PAVER WALKWAY WILL BE EXTENDED TO THE BOTTOM OF THE STAIRS

THE STAIRS WILL THEN BE FINISHED AND HANDRAILS PUT ON

THIS IS THE VIEW FROM THE GOLF COURSE

THE CONSTRUCTION FENCE WILL COME DOWN AND LANDSCAPING INSTALLED

THE WALL FOLLOWS THE PROPERTY LINE

ONCE THE WALKWAY IS IN PLACE, THE FENCE WILL COME DOWN AND LANDSCAPING INSTALLED

SCREEN PORCH ALMOST FRAMED

PLACING THE FINAL PIECES ON THE FRONT WALL

FRONT ENTRANCE IS COMPLETE EXCEPT FOR THE DOOR

GROUND HAS BEEN CLEARED FOR THE ENTRANCE WALKS

ALL A/C UNITS IN PLACE AND SECOND FLOOR UNITS RUNNING TO REDUCE HUMIDITY ON FIRST FLOOR SO DRYWALL AND PAINTING CAN CONTINUE

DECK BASE IS READY FOR PAVERS

FRONT WALL IS ALMOST COMPLETE

SOME OF FIRST FLOOR IS FINISHED EXCEPT FOR FINAL PAINT

THIS CEILING WILL BE TRIMMED IN WOOD

THE KITCHEN FLOOR IS ALMOST COMPLETE

THE MEN’S ROOM FLOOR IS ALMOST FINISHED

SECOND FLOOR IS COMPLETE AND THE CONSTRUCTION OFFICE HAS MOVED IN SO PARKING LOT CAN BE CLEARED

THE AIR HANDLERS ARE CLEAR OF THE FLOOR SPACE

SEPTEMBER 23 UPDATE

GREAT WEATHER FOR WORKING ON THE EXTERIOR

THE FRONT ENTRY IS ALMOST COMPLETE – JUST THE INSIDE TRIM IS NEEDED

THE MAIN ROOM AWAITS WINDOW TRIM, CEILING TILES, AND A SECOND COAT OF PAINT

ANOTHER SPACE ALMOST COMPLETE

BAR AREA NEEDS A LOT OF WORK

WORK ON THE DECK WALL HAS STARTED

WORK ON THE DRAINAGE SYSTEM HAS STARTED

THE UPPER LEVEL HAS THE FINAL COLORS

THE FRONT SIDING IS ALMOST COMPLETE

THE METAL ROOF IS COMPLETE

FRAMING FOR THE SCREEN PORCH HAS STARTED

SEPTEMBER 16 UPDATE

GOOD PROGRESS IS STILL BEING MADE. WIRING IS GETTING PULLED. DRYWALL IS COVERING UP AND SOME FINISH IS BEING DONE SINCE THE HUMIDITY IS LOW. A/C WILL BE RUNNING BY NEXT WEEK

EXTERIOR TRIM PAINTING IS FINISHED SO ROOFING WORK WILL FINISH NEXT WEEK. METAL ROOF GOES DOWN THURSDAY.

THE ENTRY IS TAKING SHAPE. VERY IMPRESSIVE.

THE FRONT SIDING THAT’S ON THE GROUND WILL START TO GO UP AS SOON AS THE ENTRY IS COMPLETE

SEPTEMBER 5 UPDATE – AFTER DORIAN

OLD GLORY STILL FLIES PROUDLY

DICKY SMITH IS ON SITE AND A COMPLETE INSPECTION HAS BEEN MADE

NO LEAKS – NO DAMAGE OF ANY KIND

THE LOOSE SHINGLES REMAINED IN PLACE

THE SIDING IS STILL IN THE PARKING LOT

WORK IS CONTINUING TODAY ON THE A/C UNITS IN HOPES OF TURNING THEM ON NEXT WEEK SO DRY WALL CAN CONTINUE

AUGUST 26 UPDATE

PROGRESS CONTINUES TO BE ON SCHEDULE AND ON BUDGET

THE REAR STAIRS HAVE BEEN POURED SO WORK CAN BE STARTED GRADING FOR THE WALKWAY – AND SIDING

THE STAIRS WILL BE FINISHED ALONG WITH A RAIL ONCE THE CONCRETE SETS

THE ELECTRIC PANELS ARE BEING PUT IN PLACE SO THE A/C UNITS CAN BE SET

THE UNITS WERE DELIVERED TODAY

THE PAD IS READY FOR CONCRETE

THE NORTH SIDE IS COMPLETED – DON’T WORRY, PAINTING COMES LATER

THE NORTHEAST CORNER IS ALMOST COMPLETE

THE FRONT PORCH WILL BE POURED – THEN THE SIDING WILL START

THE FRONT AREA HAS BEEN CLEANED UP FROM CONSTRUCTION SO SIDING WILL START

THE BAR HAS BEEN CLOSED IN WAITING ON THE SHUTTERS SO A/C CAN START

GRADING FOR THE DECK AREA WILL START SHORTLY – THEN THE WALL WILL START

THE SOUTH SIDE IS ALMOST COMPLETE

ONCE THE SUPPORTS ARE IN PLACE SIDING WILL START

ALL WIRING IS COMPLETE AS WELL AS PLUMBING AND FIRE

DRYWALL IS MOVING ALONG – ONCE A/C STARTS THE SECOND SIDE DRYWALL WILL GO ON AND THE MUDDING WILL START

MAIN HALLWAY IS COMPLETE

HOPE EVERYONE LIKES THE FIXTURES THE COMMITTEE PICKED OUT

SLOPPY WIRING JOB

THE KITCHEN AWAITS FIXTURES

THE ELEVATOR HAS BEEN DELIVERED AND WORK ON THAT WILL START IN ABOUT A WEEK – THEY HAVE TO FIND THE ASSEMBLY INSTRUCTIONS – OTIS SENDS THEIR OWN CREW

ALL FOR NOW – HAVE A GREAT WEEK👍👍🇺🇸🇺🇸

AUGUST 14 UPDATE

THIS IS A TEMPORARY FRONT DOOR, AS IS THE BLUE INSULATION

THE SITE IS BEING SECURED SO FINISH CAN BE COMPLETED

THE LODGE IS TAKING SHAPE, FIREPLACE IS IN, ALL EXTERIOR DOORS ARE IN PLACE

THE HALLWAY IS ALMOST COMPLETE

THE EVENT ROOMS ARE TAKING SHAPE

THE KITCHEN AREA IS ALMOST COMPLETE

THE CARD ROOM IS ALMOST COMPLETE

THE NORTH SIDE HAS BEEN COMPLETED

THE SOUTH SIDE IS ALMOST COMPLETE

THE BACK STAIRS ARE BEING PREPARED. THEY WILL BE POURED MONDAY.

THE AWNING IS TO KEEP THE RAIN OFF – IF IT COMES

THE BACK SIDING IS BEING COMPLETED

THE BACK STAIRS ARE ALMOST READY TO POUR

AUGUST 7 UPDATE

WORK IS PROGRESSING ON SCHEDULE ON MANY FRONTS

FOAM INSULATION HAS BEEN COMPLETED IN ALL ROOF AREAS

DUCT WORK IS IN FINAL STAGES

THE FIREPLACE HAS BEEN INSTALLED

MORE FOAM INSULATION

DRYWALL HAS STARTED

NORTH WALL TRIM HAS STARTED