MAY 22 UPDATE

ALL MATERIAL FOR FRAMING THE SECOND FLOOR HAS BEEN DELIVERED

STARTING WORK

FIRST FLOOR CLEANED UP

ELEVATOR SHAFT IS COMPLETE

SAFETY WALL IS FIRST PRIORITY

ELEVATOR SHAFT COMPLETE

SECOND FLOOR READY

STAIRWAY COMPLETE

SECOND FLOOR VIEW

VIEW FROM THE SOUTH

FRONT WALL IS FRAMED

MAY 14 UPDATE

THE PROJECT IS MOVING ALONG. SECOND FLOOR WALLS ARE ABOUT COMPLETE

ROOF TRUSSES SHOULD BE STARTED NEXT WEEK

REMEMBER, THE FRONT IS FRAMING, NOT CONCRETE BLOCK

AS YOU CAN SEE, WE HAVE BEEN ABLE TO RETAIN THE VERY LARGE WINDOWS FOR A GREAT VIEW

WE SHOULD BE UNDER ROOF BEFORE RAINY SEASON.

OUR CONTRACTOR HAS BEEN DOING A GREAT JOB.

MAY 7 UPDATE

THE PROJECT IS MOVING ALONG FINE.

THE SECOND FLOOR SLAB HAS BEEN POURED AND CURING

THE MASONS ARE LAYING THE BLOCK FOR THE BACK AND BOTH SIDE WALLS. THEY LAY ABOUT 1000 BLOCKS A DAY

THE SUPPORT COLUMNS WILL BE POURED EARLY THIS WEEK

THE FRAMERS WILL THEN FRAME THE FRONT WALL AND ROOF WORK WILL BEGIN

THE ROOF TRUSSES WILL BE DELIVERED WEEKS END OR EARLY NEXT WEEK

SHINGLES HAVE BEEN ORDERED AND ARE 6-8 WEEKS OUT.

ONCE UNDER ROOF WORK WILL BEGIN INSIDE

WEATHER HAS BEEN GREAT SO KEEP YOUR FINGERS AND TOES CROSSED IT CONTINUES.

IMG_0254

IMG_0252

IMG_0248

IMG_0246

IMG_0244

IMG_0243

APRIL 25 UPDATE

THE EDGE FOR POURING THE SECOND FLOOR IS COMPLETE. THIS WAS A VERY TOUGH JOB AS ALL HOLES HAD TO BE FRAMED IN TO PREVENT LOSS

CONCRETE WILL BE POURED MONDAY MORNING AT 7AM

THERE WILL BE NO TRAFFIC ISSUES AS ALL ACTIVITY WILL BE CONFINED TO THE SITE

THIS WILL TAKE A WEEK TO TEN DAYS TO CURE AND THEN THE BACK AND SIDE WALLS WILL BE BUILT USING BLOCK

AFTER THAT IS COMPLETE THE FRAMERS WILL BE ON SITE TO ERECT THE FRONT AND SET THE ROOF SUPPORT.

THE FLAG STILL PROUDLY FLIES

MORE NEXT WEEK

HOLLOW CORE UPDATE 2

THE CRANE WAS SET UP AND READY AT 7:30. THE FIRST TRUCKS ARRIVED AT 8:15

WORK CONTINUED ALL DAY WITH VERY FEW TRAFFIC DELAYS.

ALL WAS COMPLETED BY 4:30, INCLUDING GROUTING. ALL THE SEAMS BETWEEN THE SLABS ARE FILLED WITH A GROUT THAT FORMS A BOND

FOLLOW THE PICS AND CHECK THE PROGRESS. THE CONTRACTOR DID A GREAT JOB

THE NEXT STEP IS FRAMING THE SECOND FLOOR TO GET READY TO POUR THE SLAB. THIS WILL BE A TWO INCH POUR ON TOP OF THE HOLLOW CORE BASE. THIS WILL NOT HAPPEN FOR ABOUT 10 DAYS AS THE GROUT MUST CURE.

D4F996CB-271E-43BE-8274-E0AF37D5BB42

THE LARGE SLABS WERE FIRST

6B9E2011-2812-4FF0-8326-C8A429580F96

GROUTING THE SEAMS

F9E952E0-409D-4E5B-8D11-4C93D73EB761614C6B46-C8D8-4E16-AFEC-00104C55AD54549BEDB5-47AF-4ADF-B223-E33F668512B6

THE SHORT SLABS AWAIT COMPLETION OF THE LARGE ONES

8D7B33F8-2E7B-4D05-B9D2-BEEBB8DF28C1

THE TOP OUT STEEL BEAM OVER THE BAR AREA

5CE9FBB2-1984-4A35-8A69-8EAED7165C2D549B3C06-91B6-4BB8-9F0A-F8E8D9ACA200

THE MAIN ROOM

ADF73601-3444-4F92-BD4D-641E2C18E0C9

THE “CARD” ROOM AREA

760DE59D-F6F1-4943-8687-D6E80B21B766

THE LAST SMALL PIECE GOES IN PLACE

AC03098F-93A2-4D44-851F-462FC92A48AD

APRIL 14 UPDATE

A LOT OF PROGRESS THIS PAST WEEK. ALL STEEL WENT UP. THE WINDOWS HAVE BEEN FRAMED IN. THE FINAL CONCRETE BEAMS WERE POURED, AND HAVE CURED.

THE STEEL BEAMS HAVE BEEN SHORED UP SO THE HOLLOW CORE SECOND FLOOR CAN BE DROPPED IN PLACE THIS MONDAY.

THE SCREENED PORCH HAS TAKEN SHAPE WITH THE ROOF BEAMS IN PLACE.

THE HOLLOW CORE DECK FOR THE SECOND FLOOR WILL BE PUT IN PLACE MONDAY. WORK ON THE SECOND FLOOR WALLS WILL BEGIN THIS WEEK AS WELL AS POURING THE SECOND FLOOR PLATFORM.

IT IS STILL TOO EARLY TO PREDICT A COMPLETION DATE BUT THE PROJECT IS ON SCHEDULE. THE CONTRACTOR IS DOING A GREAT JOB.

41EE7501-3F5A-4B1C-B007-6112698655B2C178ED9A-F190-43E0-AE29-DBB4C9CFA4F8B193737B-116A-4448-8DE7-315A76DBE35846108839-1773-46D3-94AB-486C99590BF4B39A306B-33A5-4DAD-B49B-7D42892DBD671A27FFDD-5673-49B7-A9C0-7079A2F334729C320D93-E0A2-446A-944A-0C169D9296EFC601A5B9-8226-4E09-8CF2-D47945A90C0FC9586F44-96CB-4D06-B961-7EF8F28E54B35066FD90-DDC9-46BE-A164-CC4BDB34E109F12EEA5B-8081-4E73-B820-3D80A90DE27721CC817B-25F9-4E39-9A48-F47482C42B2326ED47EC-C96F-4CF4-BCFC-6C99742C73E721C85CC5-9E77-4EF5-99EE-966860A61BA64A56AD9E-F647-42AA-843E-2283470EC6163367DED7-8B81-4417-8BF2-7B4A10BD606B1244725E-13C2-48C6-9ADE-70E20826B007ADBD5143-CE46-4C32-8274-80A59FB2947B5A31DFD1-B8C0-417C-8C76-E7E7F9F914DAE651E8B0-5002-47DE-A9C4-559E2B89F2EB996B0CFC-3689-45B3-B262-6545FCFC672B1CCFDB7D-871A-4478-8F4E-58C82F63FB1E02B77970-865C-45D0-9F39-A68E02F3AD15CADC4D32-5C3F-4ACD-9AF4-7B493EE3526FBC477B0B-5E07-43DC-8E2B-1FB1F20EE54C3C19E392-373C-4CC2-AB87-DD7DDE016F8852719230-6F02-4CC6-BD49-02829B4DFA8C15B25338-7160-41A1-B731-531CB927D9ECFE12AFA8-1B92-48F1-BCDD-4C8FF234B2D3A8C6677A-DA76-4365-960F-F1BD920C327617193F3D-A7CD-45AE-BE03-245E59618A18FB82CB3D-EDD2-4A87-999A-44E495959F1FC31D1CB1-80E4-43E0-80D9-83F85926C158