SEPTEMBER 23 UPDATE

GREAT WEATHER FOR WORKING ON THE EXTERIOR

THE FRONT ENTRY IS ALMOST COMPLETE – JUST THE INSIDE TRIM IS NEEDED

THE MAIN ROOM AWAITS WINDOW TRIM, CEILING TILES, AND A SECOND COAT OF PAINT

ANOTHER SPACE ALMOST COMPLETE

BAR AREA NEEDS A LOT OF WORK

WORK ON THE DECK WALL HAS STARTED

WORK ON THE DRAINAGE SYSTEM HAS STARTED

THE UPPER LEVEL HAS THE FINAL COLORS

THE FRONT SIDING IS ALMOST COMPLETE

THE METAL ROOF IS COMPLETE

FRAMING FOR THE SCREEN PORCH HAS STARTED

SEPTEMBER 16 UPDATE

GOOD PROGRESS IS STILL BEING MADE. WIRING IS GETTING PULLED. DRYWALL IS COVERING UP AND SOME FINISH IS BEING DONE SINCE THE HUMIDITY IS LOW. A/C WILL BE RUNNING BY NEXT WEEK

EXTERIOR TRIM PAINTING IS FINISHED SO ROOFING WORK WILL FINISH NEXT WEEK. METAL ROOF GOES DOWN THURSDAY.

THE ENTRY IS TAKING SHAPE. VERY IMPRESSIVE.

THE FRONT SIDING THAT’S ON THE GROUND WILL START TO GO UP AS SOON AS THE ENTRY IS COMPLETE

SEPTEMBER 5 UPDATE – AFTER DORIAN

OLD GLORY STILL FLIES PROUDLY

DICKY SMITH IS ON SITE AND A COMPLETE INSPECTION HAS BEEN MADE

NO LEAKS – NO DAMAGE OF ANY KIND

THE LOOSE SHINGLES REMAINED IN PLACE

THE SIDING IS STILL IN THE PARKING LOT

WORK IS CONTINUING TODAY ON THE A/C UNITS IN HOPES OF TURNING THEM ON NEXT WEEK SO DRY WALL CAN CONTINUE

AUGUST 26 UPDATE

PROGRESS CONTINUES TO BE ON SCHEDULE AND ON BUDGET

THE REAR STAIRS HAVE BEEN POURED SO WORK CAN BE STARTED GRADING FOR THE WALKWAY – AND SIDING

THE STAIRS WILL BE FINISHED ALONG WITH A RAIL ONCE THE CONCRETE SETS

THE ELECTRIC PANELS ARE BEING PUT IN PLACE SO THE A/C UNITS CAN BE SET

THE UNITS WERE DELIVERED TODAY

THE PAD IS READY FOR CONCRETE

THE NORTH SIDE IS COMPLETED – DON’T WORRY, PAINTING COMES LATER

THE NORTHEAST CORNER IS ALMOST COMPLETE

THE FRONT PORCH WILL BE POURED – THEN THE SIDING WILL START

THE FRONT AREA HAS BEEN CLEANED UP FROM CONSTRUCTION SO SIDING WILL START

THE BAR HAS BEEN CLOSED IN WAITING ON THE SHUTTERS SO A/C CAN START

GRADING FOR THE DECK AREA WILL START SHORTLY – THEN THE WALL WILL START

THE SOUTH SIDE IS ALMOST COMPLETE

ONCE THE SUPPORTS ARE IN PLACE SIDING WILL START

ALL WIRING IS COMPLETE AS WELL AS PLUMBING AND FIRE

DRYWALL IS MOVING ALONG – ONCE A/C STARTS THE SECOND SIDE DRYWALL WILL GO ON AND THE MUDDING WILL START

MAIN HALLWAY IS COMPLETE

HOPE EVERYONE LIKES THE FIXTURES THE COMMITTEE PICKED OUT

SLOPPY WIRING JOB

THE KITCHEN AWAITS FIXTURES

THE ELEVATOR HAS BEEN DELIVERED AND WORK ON THAT WILL START IN ABOUT A WEEK – THEY HAVE TO FIND THE ASSEMBLY INSTRUCTIONS – OTIS SENDS THEIR OWN CREW

ALL FOR NOW – HAVE A GREAT WEEK👍👍🇺🇸🇺🇸

AUGUST 14 UPDATE

THIS IS A TEMPORARY FRONT DOOR, AS IS THE BLUE INSULATION

THE SITE IS BEING SECURED SO FINISH CAN BE COMPLETED

THE LODGE IS TAKING SHAPE, FIREPLACE IS IN, ALL EXTERIOR DOORS ARE IN PLACE

THE HALLWAY IS ALMOST COMPLETE

THE EVENT ROOMS ARE TAKING SHAPE

THE KITCHEN AREA IS ALMOST COMPLETE

THE CARD ROOM IS ALMOST COMPLETE

THE NORTH SIDE HAS BEEN COMPLETED

THE SOUTH SIDE IS ALMOST COMPLETE

THE BACK STAIRS ARE BEING PREPARED. THEY WILL BE POURED MONDAY.

THE AWNING IS TO KEEP THE RAIN OFF – IF IT COMES

THE BACK SIDING IS BEING COMPLETED

THE BACK STAIRS ARE ALMOST READY TO POUR

AUGUST 7 UPDATE

WORK IS PROGRESSING ON SCHEDULE ON MANY FRONTS

FOAM INSULATION HAS BEEN COMPLETED IN ALL ROOF AREAS

DUCT WORK IS IN FINAL STAGES

THE FIREPLACE HAS BEEN INSTALLED

MORE FOAM INSULATION

DRYWALL HAS STARTED

NORTH WALL TRIM HAS STARTED

JULY 29 UPDATE

THE BAR IS COMPLETELY FRAMED WAITING ON DOORS

THE MAIN DECK DOORS ARE GOING IN AS WE SPEAK

LOTS OF WALL INSULATION IS COMPLETED AND A LOT OF SOFFIT WORK DONE

WIRING HAS STARTED

SIDING ON THE SOUTH SIDE HAS BEEN STARTED

THE SCREEN PORCH IS FRAMED

DOOR INSTALLATION IN PROGRESS

UPPER WINDOWS ARE COMPLETE

ONCE THAT IS COMPLETE AND FRAMED THE LOWER ROOF WILL BE FINISHED