JUNE 8 UPDATE

THE FINAL ROOF PIECE IS STARTED – WAITING ON THE TRUSSES TO BE BUILT

ALL OTHER TRUSSES ARE IN PLACE

ROOF SHEETING HAS STARTED – FRIDAY

LOWER ROOF IS COMPLETE

STARTING ON THE UPPER

THE FRONT ENTRANCE IS TAKING SHAPE

THE ROOF SUPPORT POST SHOULD BE IN IN A COUPLE WEEKS – FOOTERS ARE POURED

FIRST FLOOR IS CLEANED UP READY FOR FRAMING TO BEGIN – POSSIBLY NEXT WEEK

FIRST FLOOR LOOKING TOWARDS THE BAR

SECOND FLOOR ROOF IS ALMOST COMPLETE

THIS IS ALL THAT IS LEFT TO SHEET AND BY THE TIME YOU GET THIS, IT WILL BE COMPLETED

OLD GLORY CONTINUES TO FLY AND WILL BE MOVED AFTER THIS SECTION IS DONE

IT WILL CONTINUE TO FLY UNTIL THE POLE GETS ERECTED

OUR GREAT WORKING SUPERINTENDENT IS KNOCKING DOWN THE SCAFFOLDING

WHILE THEY FINISH SHEETING – AND THIS IS SATURDAY

THE BLUE WATERPROOF SEAL IS ALMOST COMPLETE ALSO

MAY 31 UPDATE

FIRST FLOOR IS CLEANED UP AND ALL EXTRA SUPPORT POST ARE REMOVED

MOST ROOF TRUSSES HAVE BEEN PUT IN PLACE

ALL ROOF TRUSSES ARE IN PLACE

THE SOFFIT IS BEGINNING TO TAKE SHAPE

THE ELEVATOR SHAFT IS COMPLETE – THE BLUE IS A WEATHER SEAL

THE UPPER ROOF STRUCTURE IS COMPLETE

THE SHEETING GOES DOWN TUESDAY

MAY 22 UPDATE

ALL MATERIAL FOR FRAMING THE SECOND FLOOR HAS BEEN DELIVERED

STARTING WORK

FIRST FLOOR CLEANED UP

ELEVATOR SHAFT IS COMPLETE

SAFETY WALL IS FIRST PRIORITY

ELEVATOR SHAFT COMPLETE

SECOND FLOOR READY

STAIRWAY COMPLETE

SECOND FLOOR VIEW

VIEW FROM THE SOUTH

FRONT WALL IS FRAMED

MAY 14 UPDATE

THE PROJECT IS MOVING ALONG. SECOND FLOOR WALLS ARE ABOUT COMPLETE

ROOF TRUSSES SHOULD BE STARTED NEXT WEEK

REMEMBER, THE FRONT IS FRAMING, NOT CONCRETE BLOCK

AS YOU CAN SEE, WE HAVE BEEN ABLE TO RETAIN THE VERY LARGE WINDOWS FOR A GREAT VIEW

WE SHOULD BE UNDER ROOF BEFORE RAINY SEASON.

OUR CONTRACTOR HAS BEEN DOING A GREAT JOB.

MAY 7 UPDATE

THE PROJECT IS MOVING ALONG FINE.

THE SECOND FLOOR SLAB HAS BEEN POURED AND CURING

THE MASONS ARE LAYING THE BLOCK FOR THE BACK AND BOTH SIDE WALLS. THEY LAY ABOUT 1000 BLOCKS A DAY

THE SUPPORT COLUMNS WILL BE POURED EARLY THIS WEEK

THE FRAMERS WILL THEN FRAME THE FRONT WALL AND ROOF WORK WILL BEGIN

THE ROOF TRUSSES WILL BE DELIVERED WEEKS END OR EARLY NEXT WEEK

SHINGLES HAVE BEEN ORDERED AND ARE 6-8 WEEKS OUT.

ONCE UNDER ROOF WORK WILL BEGIN INSIDE

WEATHER HAS BEEN GREAT SO KEEP YOUR FINGERS AND TOES CROSSED IT CONTINUES.

IMG_0254

IMG_0252

IMG_0248

IMG_0246

IMG_0244

IMG_0243

APRIL 25 UPDATE

THE EDGE FOR POURING THE SECOND FLOOR IS COMPLETE. THIS WAS A VERY TOUGH JOB AS ALL HOLES HAD TO BE FRAMED IN TO PREVENT LOSS

CONCRETE WILL BE POURED MONDAY MORNING AT 7AM

THERE WILL BE NO TRAFFIC ISSUES AS ALL ACTIVITY WILL BE CONFINED TO THE SITE

THIS WILL TAKE A WEEK TO TEN DAYS TO CURE AND THEN THE BACK AND SIDE WALLS WILL BE BUILT USING BLOCK

AFTER THAT IS COMPLETE THE FRAMERS WILL BE ON SITE TO ERECT THE FRONT AND SET THE ROOF SUPPORT.

THE FLAG STILL PROUDLY FLIES

MORE NEXT WEEK